The project was won during the 1st CALL FOR OUTLINE PROPOSALS UNDER THE PLAN FOR EUROPEAN COOPERATING STATES (PECS) IN BULGARIA, September 2015
The project was conducted in the period 01 July 2016-30 August 2021. The project is completed successfully.
The Active neutron spectrometer and dosimeter (ADRON-EM) is in the list of the Russian led instruments for ExoMars 2018 Surface Platform (SP) science payload. The active neutron spectrometer of ADRON-EM instrument is under development in the Space Research Institute (IKI), Moscow. The dosimeter Liulin-ML of ADRON–EM is under development in the Space Research and Technology Institute-BAS (SRTI-BAS), Bulgaria (see Annex 1 - in Russian and http://exploration.esa.int/mars/56933-exomars-2018-surface-platform/). A participant in Liulin-ML is also the Institute of Biological and Medical Problems (IMBP-Moscow) that is responsible for the physical calibrations of the dosimeter and simulations of its response to different exposures. The PI of ADRON-EM is Igor Mitrofanov from IKI, Moscow, Russia.
The objective is to develop, manufacture, test and deliver (directly or trough ESA) to the PI of ADRON-EM the geometrical mass, thermal equivalent, engineering, qualification and flight models, the necessary hardware and software for testing and the necessary technical documentation of the dosimeter Liulin-ML of the ADRON-EM instrument for the ExoMars SP science payload. The dosimeter will be used for radiation environment monitoring onboard the Mars Surface Platform during ExoMars 2018 mission.
Compared to Objective 1 in the outline proposal - development, manufacture and testing of the qualification and flight models, the development and testing of the geometrical mass, thermal equivalent and engineering models are also added. This difference is due to the updated (during the elapsed time between the two proposals) current timeline for development, delivery and testing of the Russian led scientific payload for ExoMars SP (see the recent timeline in Annex 3a compared to the previous one in Annex 3 - in Russian). According Annex 3a the development, delivery and testing of the geometrical mass, thermal equivalent and engineering models continues to 31.10. 2016.
The Liulin-ML contains two dosimetric telescopes. Each pair of the telescopes consists of two Si PIN photodiodes and will provide absorbed dose rate, particle flux, energy deposition spectrum and linear energy transfer (LET) spectrum of primary and secondary charged particles and gamma rays aboard the SP. The combined data from Liulin-ML and the neutron detectors of ADRON-EM will be used to study the radiation conditions from all sources of ionizing radiation during the cruise phase and on the surface of Mars (functional diagram of Liulin-ML).
Data obtained will serve for verification and benchmarking of the radiation environment models and assessment of the radiation risk to the crewmembers of future exploratory flights.
The dosimeter Liulin-MO (see Annex 2) of the Fine Resolution Epithermal Neutron Detector (FREND) instrument for ExoMars TGO has been developed and manufactured in STPD-SRTI-BAS under contracts with IKI-Moscow. FREND including its dosimeter Liulin-MO has been flight qualified in IKI-Moscow, integrated and tested aboard the TGO s/c at TAS-Cannes and recently has gone final pre-launch testing aboard the TGO at Baikonur. The PI of FREND science payload is Igor Mitrofanov from IKI, Moscow, Russia.
The objective is to support the real time verification and analysis of the FREND’s dosimeter Liulin-MO data to assist with the ExoMars TGO mission planning activities.
The objective is to develop, test and provide to FREND PI and team the necessary Liulin-MO flight data products to be made available to ESA, Roscosmos and the international scientific community. The ownership of Liulin-MO data belongs to SRTI-BAS, IKI-Moscow and IMBP-Moscow. A mutual agreement between the three institutes has been signed that settles this ownership, as well as that all scientific publications based on Liulin-MO data will include the co-authors from SRTI-BAS, IKI-Moscow and IMBP-Moscow.
The objective is to survey, collect and store in unified format the existing Liulin type instruments data sets from ISS, BION, Photon and Chandrayan-1 satellites and to develop a web-based database that will serve users from all over the world. The available data of Liulin instruments is described in Annex 5. To prepare in a unified format the Liulin-MO ExoMars TGO data and to add them to the database. This will accelerate the analysis of the Liulin-MO data and will serve the ExoMars TGO team.
The geometrical (GM), thermal (TM), engineering (EM), qualification (QM) and flight (FM) models of Liulin-ML dosimeter of ADRON-EM instrument for ExoMars RSP mission, their testing equipment and design documentation has been completed, delivered to Space Research Institute-Moscow-Russia (IKI-Russia) and accepted. The design review of GM, TM, EM, QM, FM and test equipment of EM QM, FM and reviews of input acceptance tests in Bulgaria and IKI-Russia are accepted by the European Space Agency (ESA).
Liulin-ML contains two dosimetric telescopes - A&B (detectors A and B), and C&D (detectors C and D) arranged in parallel directions. Each pair of the dosimetric telescopes consists of two 300 µm thick, 20x10 mm area rectangular Si PIN photodiodes. The distance between the parallel Si PIN photodiodes is 20.8 mm. The functional diagram of the instrument is shown in Fig. 1.
|
Fig. 1. Functional diagram of Liulin-ML |
Further (during on ground data processing) the energy deposition spectrum in a single detector is obtained by combining the energy deposition spectrum measured by A or B - in the range ~ 0.15 – 47 MeV with the energy deposition spectrum measured by C or D in the range ~ 47.1 - 190 MeV. In that way the 2 pairs of two parallel detectors and their corresponding CSAs provide data in the energy deposition range ~ 0.15 - 190 MeV.
The parameters provided by Liulin-ML simultaneously for two pairs of parallel detectors have the following ranges: energy deposition spectra and coincidence energy deposition spectra in the range 0.15 - 190 MeV. The energy deposition spectra and the coincidence spectra are resolved every 130 s in fast mode and every 1 hour in standard mode of measurement.
Totally 8 spectra are measured and provided in the telemetry data: SpA, SpB, SpC, SpD – these are the energy deposition spectra in the single detectors A, B, C, D without a coincidence with signals from the other detector in the telescope; SpAB, SpBA, SpCD, SpDC - these are the coincidence spectra in the corresponding telescopes – the first letter in the name of each of these spectra indicates the detector from which the signal is measured in coincidence with the signal from the detector designated by the second letter. Each one of 8 spectra is of 1024 bytes.
In addition in 2 tables (one for the telescope A&B and the other for the telescope C&D) are recorded the spectral channel numbers of the corresponding signals from the coincidence spectra in which at least one of the coinciding signals is >20 MeV. Each table contains 32 positions and is of 64 bytes. The tables are also provided in the telemetry data.
|
Fig. 2. External view of Liulin-ML FM |
SpAB, SpBA, SpCD, SpDC and the 2 tables will be used for determination of the linear energy transfer (LET) spectra and radiation quality factors Q during on ground data processing.
All these data will be used for the calculation of the particle flux, dose rates and dose equivalent rates during on ground data processing.
The external view of Liulin-ML FM is shown in Fig.2.
|
Fig. 3. Liulin database page with data source(s) selection option and user manual |
Two separate options were foreseen in the database. By the first option the user downloads the original, zipped “DATA SOURCES” (http://esa-pro.space.bas.bg/datasources) in comma separated values (CSV) format, which are directly opened in a MS EXCEL program, where they can be easily further visualised and analysed in depth. The data sources contain the measured flux and absorbed dose rate with a resolution between 10 sec and 1 hour, the time at which the data were taken and the geographical and geomagnetic coordinates of the vehicle for each data point.
The “DATABASE” allows (http://esa-pro.space.bas.bg/database) the following functions: source selection; data export in CSV and TXT format; and several charts: visualization, synchronized zoom, tooltip and hairline; export to vector, JPEG and PDF format. The manual describes the structure of the database and its operation.
No serious technical problems raised during the design, testing and qualifications of Liulin-ML instrument for ExoMars 2020, mainly because the design of the Liulin-ML models developed and qualified for space flight under the contract was based as much as possible on the design and experience of Lulin-MO instrument already successfully flown in the space.
The main problems and risks of the contract were connected with changes of the schedule of ExoMars 2020 project as well as some technical requirements. At the beginning of the contract the planetary sterilization method for Liulin-ML was not defined. The risks were successfully resolved by communications with ESA and the international partners. Maintaining of a Risk register was helpful for this purpose.
Additional necessary works to be done, not envisaged in the original contract were identified during the work on the project and were included in 3 CCNs to the contract. These works were connected with qualification of Liulin-ML QM to FSM, development of a S/W for express analysis of Liulin-ML data during the pre-commissioning and commissioning phases of ExoMars SP, development of methods for calibrations with radioactive sources and calibration of Liulin ML QM, conducting of planetary protection procedures for Liulin-ML, continuation of the daily flight operations of Liulin-MO aboard TGO on Mars orbit, express analysis of its data, preparation and import of the running data from Liuin-MO on TGO from the Science Phase of ExoMars TGO in the Liulin data base to the end of 2019.
Close communications with ESA and the international partners for resolving the problems and risks is one of the main lessons learned.
As a follow-up of some works done under the contract, a new contract between STDP-SRTI-BAS and ESA under PECS entitled “Application of the data received from Liulin-MO dosimeter aboard ExoMars TGO (TGORad)” and based partially on Liulin-MO data processed during the contract “Dosimetry” was signed (http://esa-pro.space.bas.bg/ExoMars/).
Semkova, J., T. Dachev, St. Maltchev, B. Tomov, Yu. Matviichuk, P. Dimitrov, R. Koleva, K. Krastev, I. Mitrofanov, A. Malakhov, M. Mokrousov, A. Sanin, M. Litvak, A. Kozyrev, V. Tretyakov, D. Golovin, S. Nikiforov, A. Vostrukhin, F. Fedosov, N. Grebennikova, V. Benghinc, V. Petrov, V. Shurshakov, Radiation investigations onboard ExoMars missions. Results for radiation parameters during TGO cruise to Mars, Workshop on Radiation Measurements on ISS, ESTEC, Noordwijk, The Netherlands, 6-8 September 2016, http://www.wrmiss2016.de/
Dachev, T.P, N.G. Bankov, B. T. Tomov, Yu. N. Matviichuk, Pl. G. Dimitrov, D.-P. Häder, G. Horneck, Overview of the ISS radiation environment observed during EXPOSE-R2 mission in 2014-2016, Workshop on Radiation Measurements on ISS, ESTEC, Noordwijk, The Netherlands, 6-8 September 2016, http://www.wrmiss2016.de/
01.07.2016 - 31.08.2021

|
Code |
Task Name |
M |
Duration |
Start |
Finish |
|
|
|
ESA Project |
|
|
01-07-16 |
31-01-20 |
|
|
WP 1 |
Development of the geometrical mass, thermal equivalent, engineering and qualification models (GM, TM, EM and QM) of Liulin-ML dosimeter of ADRON-EM |
|
848 days |
01-07-16 |
01-10-19 |
|
|
Task 1.1. |
Purchase parts and materials for the EM, QM and for the testing equipment of EM and QM |
|
261 days |
01-07-16 |
30-06-17 |
|
|
Task 1.2. |
Development of the GM and TM and their design documentation |
|
130 days |
01-07-16 |
29-12-16 |
|
|
D01.01 |
Design review of GM, TM |
6 |
0 days |
30-12-16 |
30-12-16 |
|
|
Task 1.3. |
Task 1.3. Acceptance tests of GMand TM in Bulgaria |
|
151 days |
03-10-16 |
30-04-17 |
|
|
D01.02 |
Test readiness report for GM and TM |
6 |
0 days |
30-12-16 |
30-12-16 |
|
|
D01.03 |
Review on tests results of GM and TM in Bulgaria |
10 |
0 days |
30-04-17 |
30-04-17 |
|
|
Task 1.4 |
Delivery the GM and TM and the documentation, input control and acceptance tests in IKI. Analysis of the test results of GM and TM, outputs to EM, changes in the design documentation of GM and TM |
|
86 days |
30-12-16 |
15-10-17 |
|
|
D01.04 |
Delivery and qualification review of GM and TM. |
16 |
0 days |
15-10-17 |
15-10-17 |
|
|
Task 1.5. |
Development of the EM and design documentation of EM. |
|
238 days |
01-07-16 |
30-05-17 |
|
|
D01.05 |
Design review of EM |
11 |
0 days |
31-05-17 |
31-05-17 |
|
|
Task 1.6. |
Development of S/W and H/W for testing EM and its design documentation . |
|
238 days |
01-07-16 |
30-05-17 |
|
|
D01.06 |
Design review of S/W and H/W for testing EM |
11 |
0 days |
31-05-17 |
31-05-17 |
|
|
Task 1.7. |
Acceptance tests of the EM in Bulgaria |
|
153 days |
31-03-17 |
15-01-18 |
|
|
D01.07 |
Test readiness report of EM |
19 |
0 days |
15-01-18 |
15-01-18 |
|
|
D01. 08 |
Review on tests results of EM in Bulgaria |
19 |
0 days |
15-01-18 |
15-01-18 |
|
|
Task 1.8 |
Delivery the EM, test equipment and their documentation, input control and acceptance tests in IKI |
|
110 days |
01-07-17 |
01-03-18 |
|
|
D01.09 |
Delivery review of EM |
20 |
0 days |
28-02-18 |
28-02-18 |
|
|
Task 1.9 |
Testing of the EM in the integrated EM of ADRON-EM. Analysis of the test results of EM, outputs to QM and FMs, changes in the design documentation |
|
43 days |
02-10-17 |
01-03-18 |
|
|
D01. 10 |
Qualification review of EM |
20 |
0 days |
28-02-18 |
28-02-18 |
|
|
Task 1.10. |
Development of theQM and QM design documentation |
|
325 days |
01-07-16 |
01-04-18 |
|
|
D01. 11. |
Design review of QM |
21 |
0 days |
29-03-18 |
29-03-18 |
|
|
Task 1.11. |
Development of S/W and H/W for testing QM and its design documentation |
|
325 days |
01-07-16 |
01-04-18 |
|
|
D01.12. |
Design review of S/W and H/W for testing the QM. |
21 |
0 days |
29-03-18 |
29-03-18 |
|
|
Task 1.12. |
Testing and acceptance tests of QM in Bulgaria . |
|
65 days |
01-01-19 |
01-04-19 |
|
|
D01.13 |
Test readiness report on QM. |
33 |
0 days |
29-03-19 |
29-09-19 |
|
|
D01.14 |
Review on tests results of QM in Bulgaria |
33 |
0 days |
29-03-19 |
29-03-19 |
|
|
Task 1.13 |
Delivery the QM, the QM test equipment and their documentation, input control and acceptance tests in IKI |
|
21 days |
29-03-19 |
01-05-19 |
|
|
D01.15 |
Delivery review of QM. |
34 |
0 days |
30-04-19 |
30-04-19 |
|
|
Task 1.14. |
Testing the QM in the integrated QM of ADRON-EM in IKI. |
|
87 days |
01-05-19 |
01-09-19 |
|
|
D01.16 |
Review on qualification and resource tests of QM |
38 |
0 days |
28-08-19 |
28-08-19 |
|
|
Task 1.15 |
Analysis of the test results of QM, outputs to FMs, changes in the design documentation |
|
129 days |
02-10-19 |
01-11-19 |
|
|
D01.17 |
Qualification review of QM |
39 |
0 days |
30-09-19 |
30-09-19 |
|
|
WP 2 |
Development of the flight (FM) model of Liulin-ML dosimeter of ADRON-EM |
|
848 days |
01-07-16 |
01-10-19 |
|
|
Task 2.1 |
Purchase parts and materials for the FM and for the testing equipment of FM |
|
456 days |
01-07-16 |
30-03-18 |
|
|
Task 2.2. |
Development of FM and design documentation of FM |
|
498 days |
01-07-16 |
29-05-18 |
|
|
D02.01. |
Design review of FM |
23 |
0 days |
30-05-18 |
30-05-18 |
|
|
Task 2.3. |
Development of S/W, and H/W for testing of FM and its design documentation. |
|
498 days |
01-07-16 |
29-05-18 |
|
|
D02.02. |
Design review of S/W and H/W for testing and calibrations of FM |
23 |
0 days |
30-05-18 |
30-05-18 |
|
|
Task 2.4. |
Testing and acceptance tests of FM in Bulgaria |
|
107 days |
31-04-19 |
30-07-19 |
|
|
D02.03 |
Test readiness report for FM |
36 |
0 days |
30-06-19 |
30-06-19 |
|
|
D02.04 |
Review of FM test results in Bulgaria |
37 |
0 days |
29-07-19 |
29-07-19 |
|
|
Task 2.5 |
Delivery the FM, the FM test equipment and their documentation, input control and acceptance tests in IKI. |
|
194 days |
01-07-19 |
31-07-19 |
|
|
D02.05 |
FM delivery review |
37 |
0 days |
30-07-19 |
30-07-19 |
|
|
Task 2.6 |
Testing the FM model in the integrated FM of ADRON-EM in IKIand NPO Lavochkin. |
|
194 days |
31-08-19 |
30-09-19 |
|
|
D02.06 |
Review on test results of FM in the integrated FM of ADRON-EM |
39 |
194 days |
30-09-19 |
30-09-19 |
|
|
Task 2.7. |
Analysis of the tests and calibration results of FM, changes in the design documentation of the FM if necessary |
|
194 days |
15-09-19 |
30-09-19 |
|
|
D02.07 |
Qualification review of FM |
39 |
0 days |
30-09-19 |
30-09-19 |
|
|
WP 3 |
Flight operations of Liulin-MO dosimeter of FREND instrument on ExoMars TGO |
|
499 days |
01-07-16 |
30-05-18 |
|
|
Task 3.1. |
Design and development of software for producing quick-looks |
|
64 days |
01-07-16 |
28-09-16 |
|
|
D03.01 |
Code and user manual for graphical presentation of the data |
3 |
0 days |
29-09-16 |
29-09-16 |
|
|
Task 3.2. |
Verification and analysis of Liulin-MO science results during the cruise phase of TGO mission |
|
129 days |
01-07-16 |
28-12-16 |
|
|
D03.02 |
Review of Liulin-MO performance during TGO cruise phase |
6 |
0 days |
29-12-16 |
29-12-16 |
|
|
Task 3.3. |
Real time verification and analysis of Liulin-MO science results during the science phase of TGO |
|
498 days |
01-07-16 |
29-05-18 |
|
|
D03.03 |
Review of Liulin-MO performance during TGO science phase |
23 |
0 days |
30-05-18 |
30-05-18 |
|
|
WP 4 |
Handling the data from the dosimeter Liulin-MO of FREND instrument on ExoMars TGO |
|
2957 days |
28-02-07 |
29-06-18 |
|
|
Task 4.1. |
Numerical calculation of the instrument response function |
|
64 days |
01-07-16 |
28-09-16 |
|
|
D04.01 |
Precise calibration information about Liulin-MO |
3 |
0 days |
29-09-16 |
29-09-16 |
|
|
Task 4.2 |
Creating the software for final data processing |
|
171 days |
01-07-16 |
24-02-17 |
|
|
D04.02 |
Code and user manual for final data processing |
8 |
0 days |
28-02-07 |
28-02-07 |
|
|
Task 4.3 |
Create and deliver to FREND PI scientific data products obtained during the commission and cruise phase |
|
215 days |
01-07-16 |
27-04-17 |
|
|
D04.03 |
Review oft science results obtained during the commission and cruise phase |
10 |
0 days |
28-04-17 |
28-04-17 |
|
|
Task 4.4 |
Create and deliver to FREND PI scientific data products obtained during the science phase |
|
520 days |
01-07-16 |
28-06-18 |
|
|
D04.04 |
Review of science results obtained during the science phase |
24 |
0 days |
29-06-18 |
29-06-18 |
|
|
WP 5 |
Development of uniform, web-based database with the Liulin data |
|
499 days |
01-07-16 |
31-05-18 |
|
|
Task 5.1 |
Survey, classification and definition of relevant data |
|
86 days |
01-07-16 |
28-10-16 |
|
|
D05.01 |
Existing radiation experiments data classified and cross calibrated for relevant parameters. Review. |
4 |
0 days |
31-10-16 |
31-10-16 |
|
|
Task 5.2 |
Data recovery and formatting |
|
130 days |
01-07-16 |
29-12-16 |
|
|
D05.02 |
Formatted and recovered data, Review and description. |
6 |
0 days |
30-12-16 |
30-12-16 |
|
|
Task 5.3 |
Data cross exploitation with the satellite coordinates |
|
195 days |
01-07-16 |
30-03-17 |
|
|
D05.03 |
Liulin radiation data tabled together with the time and space data. Description. |
9 |
0 days |
31-03-17 |
31-03-17 |
|
|
Task 5.4 |
Establishment of data quality assurance |
|
261 days |
01-07-16 |
30-06-17 |
|
|
D05.04 |
Data quality assured. Review and description. |
12 |
0 days |
03-07-17 |
03-07-17 |
|
|
Task 5.5 |
User requirements analysis; I/O Interfaces development. |
|
390 days |
01-07-16 |
28-12-17 |
|
|
D05.05 |
User and system specifications; I/O Interfaces and software. Review and description. |
18 |
0 days |
29-12-17 |
29-12-17 |
|
|
Task 5.6 |
Uniform database software development; Beta version running |
|
455 days |
01-07-16 |
29-03-18 |
|
|
D05.06 |
Software, Data formatted for delivery and database; Beta version Review and description. |
21 |
0 days |
30-03-18 |
30-03-18 |
|
|
Task 5.7 |
Final uniform database running |
|
499 days |
01-07-16 |
30-05-18 |
|
|
D05.07 |
Validated uniform database. User manual. |
23 |
0 days |
31-05-18 |
31-05-18 |
|
|
WP 6 |
Management and reporting |
|
1348 days |
01-07-16 |
31-08-2021 |
|
|
Task 6.1 |
Project management and reporting |
|
631 days |
01-07-16 |
30-11-18 |
|
|
D06.01.1 |
Risk register and I Progress report |
3 |
0 days |
30-09-16 |
30-09-16 |
|
|
D06.02 |
Project Website online |
3 |
0 days |
30-09-16 |
30-09-16 |
|
|
D06.01.2 |
II progress report and Risk register updated delivery |
6 |
0 days |
30-12-16 |
30-12-16 |
|
|
D06.03.1 |
III progress report and Risk register updated delivery |
9 |
0 days |
31-03-17 |
31-03-17 |
|
|
D06.03.2 |
IV progress report and Risk register updated delivery |
12 |
0 days |
30-06-17 |
30-06-17 |
|
|
D06.04.1 |
V progress report and Risk register updated delivery |
15 |
0 days |
29-09-17 |
29-09-17 |
|
|
D06.04.2 |
VI progress report and Risk register updated delivery |
18 |
0 days |
29-12-17 |
29-12-17 |
|
|
D06.04.3 |
VII progress report and Risk register updated delivery |
21 |
0 days |
30-03-18 |
30-03-18 |
|
|
D06.05 |
VIII progress report and Risk register updated delivery |
24 |
0 days |
29-06-18 |
29-06-18 |
|
|
D06.06 |
IX progress report and Risk register updated delivery |
27 |
0 days |
28-09-18 |
28-09-18 |
|
|
Task 6.2 |
Preparation and delivery of Technical Data Package |
|
17 days |
01-08-2021 |
21-08-2021 |
|
|
D06.07 |
Technical Data Package Delivery |
42 |
0 days |
21-08-2021 |
21-08-2021 |
|
|
Task 6.3 |
Preparation and delivery of Final Report |
|
17 days |
01-08-2021 |
21-08-2021 |
|
|
D06.08 |
Final Report Delivery |
42 |
0 days |
21-08-2021 |
21-08-2021 |
|
|
Task 6.4 |
Preparation and delivery of Executive Summary Report |
|
17 days |
01-08-2021 |
21-08-2021 |
|
|
D06.09 |
Executive Summary Report Delivery |
42 |
0 days |
21-08-2021 |
21-08-2021 |
|
|
Task 6.5 |
Contractual management |
|
1348 days |
01-07-16 |
31-08-2021 |
|
|
Task 6.6 |
Resources management |
|
1348 days |
01-07-16 |
31-08-2021 |
|
|
|
PLANNING of CONTRACT CHANGE NOTICE No. 01 (CCN01) |
|
|
|
|
|
|
WP 7 |
Continuation of pre-launch works for QM and FM of Liulin-ML dosimeter on ExoMars 2020 SP |
|
107 days |
15-04-19 |
10-12-19 |
|
|
Task 1.1. |
Calibration of QM. Development of a S/W, analysis of the calibration results. |
|
87 days |
15-04-19 |
13-08-19 |
|
|
TN01.01 |
Review of calibrations method, S/W and results |
4 |
0 days |
12-08-19 |
12-08-19 |
|
|
Task 1.2. |
Environmental protection of QM. Analysis of the QM performance after sterilization. Input for FM |
|
44 days |
15-04-19 |
13-08-19 |
|
|
TN01.02 |
Review on the microbiological assays and operation of Liulin-ML QM after sterilization |
4 |
0 days |
12-06-19 |
12-08-19 |
|
|
Task 1.3. |
Task 1.3. Environmental protection of FM. Analysis of FM performance after sterilization |
|
45 days |
10-07-19 |
10-12-19 |
|
|
TN01.03 |
Review on the microbiological assays and operation of FM after sterilization works |
8 |
0 days |
11-09-19 |
09-12-19 |
|
|
WP 8 |
Flight operations and handling the data of the dosimeter Liulin-MO of FREND instrument on ExoMars TGO |
|
237 days |
15-04-19 |
10-12-19 |
|
|
Task 2.1 |
Verification of Liulin-MO performance during the science phase of TGO |
|
129 days |
15-04-19 |
10-12-19 |
|
|
TN02.01 |
Review of Liulin-MO performance during the 10th –15th months of TGO science phase. |
4 |
0 days |
15-04-19 |
12-08-19 |
|
|
Task 2.2 |
Import of Liulin-MO data obtained during TGO science phase into the Unified web-based database with Liulin type instruments cosmic radiation data |
|
42 days |
14-10-19 |
10-12-19 |
|
|
TN02.02 |
Review of the importation of Liulin-MO data into the Unified web-based database with Liulin type instruments cosmic radiation data |
8 |
0 days |
10-12-19 |
10-12-19 |
|
|
WP 9 |
Management and reporting |
|
259 days |
15-04-19 |
10-12-19 |
|
|
Task 3.1 |
Project management and reporting. Contractual management. Resources management |
|
259 days |
15-04-19 |
10-12-19 |
|
|
TN 03.01 |
Project Website updated |
2 |
0 days |
13-06-19 |
13-06-19 |
|
|
|
CCN01 I Progress report and Risk register |
3 |
0 days |
15-07-19 |
15-07-19 |
|
|
|
CCN01 II Progress report and Risk register |
6 |
0 days |
15-10-19 |
15-10-19 |
|
|
|
CCN01 III Progress report and Risk register |
8 |
0 days |
16-12-19 |
16-12-19 |
|
| Code | Task Name | Duration | Start | Finish | |
| WP 10 | Qualification of FM and FSM for launch on ExoMars 2020 SP | 185 days | 17-12-19 | 31-08-20 | |
| Task 10.1. | Qualification of the Liulin-ML QM to Flight Spare Model (FSM) in compliance with the Russian requirements for this procedure. Additional sterilization of FSM and analyses of Liulin-ML FSM operation after that (if necessary).. | 129 days | 02-01-20 | 30-06-20 | |
| TN10.01 | Report on the qualification results of QM to FSM accompanied by a protocol signed by the Russian partners | 0 days | 30-06-20 | 30-06-20 | |
| WP 11 | Qualification of Liulin-ML to TRL9 | 304 days | 01-07-20 | 30-08-21 | |
| Task 11.1 | Verification of Liulin-ML performance during the pre-commissioning and commissioning phases of SP | 284 days | 01-07-20 | 02-08-21 | |
| TN 11.01 | Description of the S/W for express analysis of Liulin-ML data. | 0 days | 15-09-20 | 15-09-20 | |
| WP 12 | Management and reporting | 185 days | 17-12-19 | 31-08-20 | |
| Task 12.01 | Project management and reporting. Contractual management. Resources management | 185 days | 17-12-19 | 31-08-20 | |
| TN 12.01 | Project Website updated | 0 days | 15-02-20 | 15-02-20 | |
| CCN02 I Progress report and Risk register | 0 days | 20-03-20 | 20-03-20 | ||
| CCN02 II Progress report and Risk register | 0 days | 25-06-20 | 25-06-20 | ||
| CCN02 III Progress report and Risk register | 0 days | 30-09-20 | 30-09-20 | ||
| CCN02 IV Progress report and Risk register | 0 days | 30-12-20 | 30-12-20 | ||
| CCN02 V Progress report and Risk register | 0 days | 30-03-21 | 30-03-21 | ||
| CCN02 VI Progress report and Risk register | 0 days | 30-06-21 | 30-06-21 |